Project
High Tech Office Space
Customer
KRP High Tech Firm
Location
Kanata, ON
Date
Oct 10, 2022
Service
Compressed Schedule Large Scale D&I
Size
32,000 SF
High Tech, Private Sector
Project Details
122 HA benching stations, 22 power poles, 90 lockers, full kitchenette, multiple boardrooms, wall-mounted glassboards, breakout areas, phone booths, filing islands, 200+ pce seating ... 5 days
By all accounts this was to be just another routine installation. But between significant construction delays and a budding startup company committed to moving staff and their contents into their workspace on a firm and unchangeable date - our schedule went from twelve business days to five calendar days. Our intermarket dealership customer was looking for solutions not complaints.
Our storage capability solved the problem of where to house the several truckloads of product while the site was being completed. But concerns around the daunting amount of work required - 112 HA benching stations, 22 power poles, 90 lockers, full kitchenette with casework, multiple boardrooms, wall mounted glassboards, breakout areas, filing islands, several phone booths and a few-hundred pieces of seating, we needed an immediate solution. It was a furniture emergency.
Consolidated Office delivered by drawing on resources from our other branches and our sister moving company, essentially flooding the site and working long shifts, with focus on the end user’s need to be ‘live’ on the first day in their new space. This cemented our relationship serving one of Canada’s largest suppliers of office furnishings, which we are honoured to maintain today.